Preliminary Renovation Phases
September 3, 2010
Phase 1 – Estimated start date is the week of September 13th.
1. West stoop removed and foundation waterproofed
2. Unisex bathroom built; followed by renovation of two primary bathrooms
3. Install new windows in education wing
4. Demo exterior walls (and beam area) in Worship Hall and Friendship Hall.
5. Install trapezoidal windows in Friendship Hall; finish interior renovations of north side of Worship Hall.
Phase 2 will renovate the south side of the education wing
1. Build temp wall down the education wing hall; renovate all rooms on south side of hallway.
2. Replace all mechanicals.
Phase 3: will renovate north side of education wing, including new offices and enlarged music room
Phase 4:
1. Finish work in the Friendship Hall,
2. Remodel old office space into adult meeting and meditation space
3. Complete refurbishing Welcome Space